Group project
Power backup and air conditioning

Application
Supply, installation and commissioning of the power backup and air conditioning system for the data center of the BCV headquarters in Maracaibo.
Project scope
- 100 kVA industrial UPS in redundant parallel
- Lead-acid battery bank
- 300 kVA power plant
- Precision air conditioning
- Civil works, testing and commissioning
Why EGC?
- Contracting capacity
- Alliance with ABB, Pramac, Ever Exceed and Aermec
- Technical know-how